Britain's fast-tracked grid

All 26 accelerated transmission projects across the three licences. Where the dates have moved, which allowances are public, what money has gone out before assessment, and where each one is in planning.

Britain is building new high-voltage lines and subsea cables to move electricity, much of it offshore wind, to where it gets used. In December 2022 Ofgem put 26 of these projects on a fast track, the Accelerated Strategic Transmission Investment framework. In August 2023 it wrote each one into the licence of the company that has to build it: a delivery date and an allowance, the cost Ofgem accepts for the job. Three companies hold those licences. National Grid Electricity Transmission covers England and Wales. Scottish Hydro Electric Transmission covers the north of Scotland, SP Transmission the south.

This is the state of the programme on 17 September 2026. The 26 projects, their dates and how the dates have moved, which allowances are public, what money has gone out before assessment, where each project is in planning, who is bound, and the licence rules behind it. Second report from the web, first on one part of it. I re-issue it as the autumn decisions land.

What the programme is

Ofgem's December 2022 decision applied the framework to an initial 26 projects worth £19.8bn. On 25 August 2023 it modified all three transmission licences to add a deliverable table. Each row is an output with a delivery date and an allowance. The web holds every row of the three tables as a commitment, in the August 2023 version and in the September 2026 consolidations from Ofgem's public register, with the 2022 decision's own date for each project next to it.

Three tables, 31 rows, 26 projects. Five projects sit in two licences because they are joint ventures: Eastern Green Link 1 (NGET and SPT), Eastern Green Link 2 (NGET and SHET), Eastern Green Links 3 and 4 (all three), East Coast Onshore Phase 2 (the two Scottish owners). NGET's table has 17 rows, SHET's 10, SPT's 4. NGET calls its 17 The Great Grid Upgrade. Its May 2026 statement to the Planning Inspectorate says so in those words: 17 major projects delivered under the framework.

The register

Owners are the committing licensees. The three date columns are the 2022 decision's optimal date, the first licence date of August 2023, and the licence date today.

Code Output Owners 2022 optimal Aug 2023 licence Sept 2026 licence Allowance
E2DC Eastern Green Link 1, Torness to Hawthorn Pit HVDC NGET, SPT 2027 31 Dec 2028 31 Dec 2028 decided
HWUP Hackney, Tottenham and Waltham Cross uprating NGET 2027 31 Dec 2028 31 Dec 2028 not published
OPN2 Yorkshire GREEN, Norton, Osbaldwick and Monk Fryston NGET 2027 31 Dec 2028 31 Dec 2028 decided
BTNO Bramford to Twinstead NGET 2028 31 Dec 2029 31 Dec 2029 not published
DWNO Denny to Wishaw 400 kV SPT 2028 31 Dec 2029 31 Dec 2029* not published
EDEU Brinsworth, Chesterfield and High Marnham NGET 2028 31 Dec 2029 31 Dec 2029 not published
PTC1 Pentir to Trawsfynydd cable replacement NGET 2028 31 Dec 2029 31 Dec 2029 not published
TKRE Tilbury to Grain and Tilbury to Kingsnorth NGET 2028 31 Dec 2029 31 Dec 2029 not published
E4D3 Eastern Green Link 2, Peterhead to Drax HVDC NGET, SHET 2029 31 Dec 2030 31 Dec 2030 decided
PTNO North Wales reinforcement NGET 2029 31 Dec 2030 31 Dec 2030 not published
AENC Norwich to Tilbury, north East Anglia circuit NGET 2030 31 Dec 2031 31 Dec 2031 not published
ATNC Norwich to Tilbury, south East Anglia circuit NGET 2030 31 Dec 2031 31 Dec 2031 not published
BBNC Beauly to Blackhillock 400 kV double circuit SHET 2030 31 Dec 2031 31 Dec 2031 not published
BDUP Beauly to Denny uprate to 400 kV SHET 2030 31 Dec 2031 31 Dec 2031 not published
BIDC Arnish to Beauly HVDC (Western Isles) SHET 2030 31 Dec 2031 31 Dec 2031 not published
BLN4 Beauly to Loch Buidhe 400 kV SHET 2030 31 Dec 2031 31 Dec 2031 not published
BPNC Blackhillock to Peterhead 400 kV double circuit SHET 2030 31 Dec 2031 31 Dec 2031 not published
CGNC North Humber to High Marnham (Creyke Beck to the south Humber) NGET 2030 31 Dec 2031 31 Dec 2031 not published
EDN2 Chesterfield to Willington (formerly Ratcliffe-on-Soar) NGET 2030 31 Dec 2031 31 Dec 2031 not published
PSDC Spittal to Peterhead HVDC SHET 2030 31 Dec 2031 31 Dec 2031 not published
SCD1 Sea Link, Suffolk to Kent HVDC NGET 2030 31 Dec 2031 31 Dec 2031 not published
SLU4 Loch Buidhe to Spittal 400 kV SHET 2030 31 Dec 2031 31 Dec 2031 not published
TKUP East Coast Onshore 400 kV Phase 2 SHET, SPT 2030 31 Dec 2031 31 Dec 2031 not published
GWNC Grimsby West to Walpole NGET 2030 31 Dec 2031 31 Dec 2033 not published
E4L5 Eastern Green Link 3, Peterhead to West Norfolk HVDC NGET, SHET, SPT 2030 31 Dec 2031 31 Aug 2034 not published
TGDC Eastern Green Link 4, East Scotland to West Norfolk HVDC NGET, SHET, SPT 2030 31 Dec 2031 31 Aug 2034 not published

*Denny to Wishaw's date comes from the table Ofgem annexed to its 12 May 2026 decision. The September 2026 SP Transmission licence does not carry SPT's rows in its own table. See the licences section.

Dates

Figure 1. Thirteen of the twenty-six fall due on the last day of 2031Licence delivery dates as at September 2026, by NOA code.

Redesigned in December 2025, and the only outputs to have moved since 2023

  1. 31 December 2028E2DCHWUPOPN23
  2. 31 December 2029BTNODWNOEDEUPTC1TKRE5
  3. 31 December 2030E4D3PTNO2
  4. 31 December 2031AENCATNCBBNCBDUPBIDCBLN4BPNCCGNCEDN2PSDCSCD1SLU4TKUP13
  5. 31 December 2033GWNC1
  6. 31 August 2034E4L5TGDC2

Source: UK electricity grid map, 17 September 2026

Ten of the 26 are due by the end of 2030, inside the current price control, which ends on 31 March 2031. Thirteen are due on the last day of 2031. The last three carry dates Ofgem set on 9 December 2025 after the owners asked for a scope change, consulted on from 11 September 2025.

Figure 2. Twenty-three of the twenty-six still carry the date they were given in 2023Movement from the 2022 optimal date to the current licence date.
  • One year laterevery output except the three below23 outputs
  • Four years laterEGL3, EGL42 outputs
  • Three years laterGWNC1 outputs

Source: UK electricity grid map, 17 September 2026

The 2022 decision gave each project a year under the heading Optimal Date, with a note that some of those years were earlier than the owners' own estimates. When the tables went into the licences in August 2023, all 26 got a delivery date one year after the optimal date, at the end of that year. Since August 2023 only the three redesigned projects have moved. The other 23 still carry their 2023 date.

The licence adds a year on top. The licensee must deliver no later than 12 months after the date in the table.

Allowances

Three outputs carry a figure.

Output Printed in the licence Project assessment decision Price base Decision date
Eastern Green Link 1 (E2DC) £2,492,205,963 £2,001,104,429 GBP 15 Nov 2024
Eastern Green Link 2 (E4D3) £4,295,638,278 £3,449,161,471 GBP 13 Aug 2024
Yorkshire GREEN (OPN2) £368,126,448 £295,585,307 2018/19 prices 8 Nov 2024
Figure 3. Twenty-three of the twenty-six have no published allowanceA figure becomes public only when Ofgem publishes a project assessment decision.
  • Not publishedvalue sits in the ASTI Confidential Annex23 outputs
  • DecidedE2DC, E4D3, OPN23 outputs

Source: UK electricity grid map, 17 September 2026

Twenty-three of the 26 have no published allowance. For each, the licence column reads "Have the values given in the ASTI Confidential Annex." The licence defines that annex as a confidential document Ofgem issues to the licensee. A figure becomes public when Ofgem publishes a project assessment decision, and a licensee can only apply for one once all its main planning applications are in. Three projects have got there. In each case the figure printed in the licence is higher than the figure in the decision. Both are above. Nothing in the web says what the difference is, so I do not explain it here. Two more assessments have been consulted on, Bramford to Twinstead and Hackney. Sea Link's is under consultation. No consultation figure appears in this report.

Funding ahead of assessment

Before assessment a licensee can apply for early construction funding. The licence caps it at 20 percent of the forecast cost in the unpublished annex unless Ofgem directs otherwise. Ofgem has decided such funding for 22 of the 26. The percentages below are Ofgem's words. Where a decision gives the share against both the 2022 licence cost base and the owner's updated forecast, both are shown as printed.

Code Latest decision Date
HWUP ECF approved at 20.2% of total forecast project cost 13 Aug 2024
DWNO ECF round 2 approved: cumulative 55% of licence project cost (24% of SPT's updated cost forecast) 12 May 2026
EDEU ECF approved in full: 104% of the licence project cost estimate, 25% of the updated project cost estimate 3 Feb 2026
PTC1 further ECF approved: 14% requested on top of 6% previously approved, up to the 20% cap (PTC1 and PTNO as a single construction project) 3 Feb 2026
TKRE ECF approved; minded-to position of 19.29% of total forecast project cost maintained 21 Oct 2024
PTNO further ECF approved: 14% requested on top of 6% previously approved, up to the 20% cap (PTC1 and PTNO as a single construction project) 3 Feb 2026
AENC ECF allowance amended to 65.93% of the AENC project value listed in the Confidential Annex (combined Norwich-Tilbury ECF 45.5% of the AENC and ATNC value) 3 Feb 2026
ATNC ECF allowance amended to 39% of the ATNC project value listed in the Confidential Annex (no ECF previously granted for ATNC) 3 Feb 2026
BBNC ECF round 3 approved: cumulative 14% of licence project cost (5% of SHET's updated cost forecast) 12 May 2026
BDUP ECF round 3 approved: cumulative 44% of licence project cost (10% of SHET's updated cost forecast) 12 May 2026
BIDC ECF round 3 approved: cumulative 23% of licence project cost (9% of SHET's updated cost forecast) 12 May 2026
BLN4 ECF round 3 approved: cumulative 30% of licence project cost (7% of SHET's updated cost forecast) 12 May 2026
BPNC ECF round 3 approved: cumulative 27% of licence project cost (7% of SHET's updated cost forecast) 12 May 2026
CGNC ECF approved up to the 20% cap of project cost as set out in NGET's licence 3 Feb 2026
EDN2 ECF approved up to the 20% cap of project cost as set out in NGET's licence 3 Feb 2026
PSDC ECF round 3 approved: cumulative 19% of licence project cost (9% of SHET's updated cost forecast) 12 May 2026
SCD1 ECF approved at 48% of the forecast project cost of SCD1 in the ASTI Confidential Annex (27% of the updated cost forecast) 19 Nov 2025
SLU4 ECF round 3 approved: cumulative 34% of licence project cost (6% of SHET's updated cost forecast) 12 May 2026
TKUP ECF round 1 (SPT portion) approved: 53% of licence project cost (application 72%) 12 May 2026
GWNC ECF approved up to the 20% cap, calculated on the updated total project costs after the material scope change 3 Feb 2026
E4L5 ECF approved at 8% of the updated total forecast project cost 9 Dec 2025
TGDC ECF approved at 13% of the updated total forecast project cost 9 Dec 2025

The four without a decision are the three already assessed and Bramford to Twinstead. Twelve of the latest shares are above the 20 percent cap on the 2022 base, by direction. Ten decisions also give the share against the owner's updated forecast, 5 to 27 percent. The gap between the two shares is the only public measure of how far the forecasts have moved from the 2022 bases.

Consenting

Eleven outputs are on the Planning Inspectorate's register of nationally significant projects, across nine project pages, each with a downloadable boundary file. Fifteen are not. Six of NGET's go through councils and the marine licensing body. The nine Scottish outputs are consented under Scottish law, which I have not yet searched.

Code Register reference Stage Boundary file
HWUP EN020009 post-decision yes
OPN2 EN020024 post-decision yes
BTNO EN020002 post-decision yes
AENC EN020027 recommendation yes
ATNC EN020027 recommendation yes
CGNC EN020034 pre-application yes
EDN2 EN0210001 pre-application yes
SCD1 EN020026 decision yes
GWNC EN020036 pre-application yes
E4L5 EN0210003 pre-application yes
TGDC EN0210003 pre-application yes

Two statutory dates fall this autumn. The Secretary of State's decision on Sea Link is due by 30 October 2026. The examining authority's recommendation on Norwich to Tilbury is due by 10 November 2026. Hackney runs on a 2014 order that NGET applied to amend in May 2026. Yorkshire GREEN was consented in March 2024, Bramford to Twinstead in September 2024.

Names, parties and structure

The licence names each output by code and description. The owners and the register use project names. All 26 are tied to a project name by an Ofgem document. Ofgem renamed Chesterfield to Ratcliffe-on-Soar as Chesterfield to Willington in February 2026. The Western Isles link got the code BIDC in Ofgem's decisions from November 2025; the licence still prints no code for it.

Thirteen outputs bind NGET alone, seven SHET alone, one SPT alone, five are joint. Counterparties on file where a contract or designation is public: Prysmian on Eastern Green Links 1 and 2, Hitachi Energy and Royal BAM on Eastern Green Link 2, NKT as preferred supplier on Eastern Green Link 3.

Figure 4. Twenty-four of the twenty-six pull on a transmission substationNodes the 26 outputs place demand on.
  • National transmission system26 outputs
  • Transmission substation24 outputs
  • High-voltage overhead line15 outputs
  • Underground cable circuit8 outputs
  • HVDC cable7 outputs
  • HVDC converter station7 outputs
  • HVDC transmission link7 outputs
  • XLPE cable insulation4 outputs
  • High-voltage switchgear3 outputs
  • Transmission tower3 outputs
  • Converter station civils1 outputs
  • Insulation and interruption gas1 outputs
  • Overhead line conductor1 outputs
  • Power transformer1 outputs

Source: UK electricity grid map, 17 September 2026

The licences themselves

Forty-two facts hold the rules, each quoted from the September 2026 NGET licence with its paragraph number, and from the 2023 modification where the wording matches. The allowance is the Appendix 1 figure. Delivery is due within 12 months of the table date. Early construction funding is capped at 20 percent unless directed. Assessment follows the planning applications. The cost-adjustment threshold is 5 percent, with 1 percent for Eastern Green Link 1 and 0.75 percent for Eastern Green Link 2 added in 2026. The delivery incentive rewards or penalises against a target date, with a penalty exemption of zero days. The condition was numbered 3.41 in 2023 and is 3.21 now; the licence's own definitions still cite the old numbers.

Two things about the published documents I record as facts. SHET's September 2026 licence prints 31 August 2034 for Eastern Green Link 3. The table Ofgem annexed to its May 2026 decision still printed 31 December 2031. The current licence settles it. SP Transmission's September 2026 licence prints the ten SHET rows in the table that should hold SPT's four outputs. SPT's own outputs appear only in the incentive table: Denny to Wishaw 31 December 2029, Eastern Green Link 1 31 December 2028, Eastern Green Link 4 31 August 2034, East Coast Onshore Phase 2 31 December 2031. I hold no delivery date for SPT's rows from that document and say so.

What changed since the September web report

The 13 September web report held 17 outputs from one licence, three public allowances and 14 allowance gaps, each recording a search of the licence alone. On 17 September I added 688 facts, 80 sources, 9 commitments, 2 instruments and 46 events: the nine Scottish outputs, the 2022 and 2023 dates for all 26, the two current Scottish licences, one more decided allowance, the funding decisions, the consent register and its events, the name ties, and the licence rules. The web now holds 2,035 live facts, 312 sources, 55 commitments, 61 events and 478 recorded gaps.

What to watch

Sea Link's decision, due by 30 October 2026. Norwich to Tilbury's recommendation, due by 10 November 2026. The assessment decisions for Bramford to Twinstead and Hackney, both consulted on and pending, and Sea Link's, under consultation. The first assessment submission from a Scottish owner; none of the nine has one. Each changes a row above. I re-issue the report when one does.

Sources

  • Ofgem: the NGET, SHET and SPT electricity transmission licence Special Conditions, September 2026 consolidations (Electronic Public Register); the decision of 25 August 2023 modifying the three licences for ASTI and its three annexes; the decision on accelerating onshore electricity transmission investment of 15 December 2022; project assessment decisions for Eastern Green Link 2 (13 August 2024), Eastern Green Link 1 (15 November 2024) and Yorkshire GREEN (8 November 2024); early and pre-construction funding decisions for the NGET outputs (2023 to 2026) and the Scottish outputs (2024 to 2026); the material scope change decision of 9 December 2025 and its consultation of 11 September 2025; the SPT licence modification notice of 5 December 2025.
  • Planning Inspectorate: the national infrastructure register pages for the eleven outputs on it, the register's applications download, and the decision notice for the North London reinforcement; DESNZ decision letters for Yorkshire GREEN and Bramford to Twinstead.
  • National Grid Electricity Transmission plc: Annual Report and Accounts 2025/26; the supporting statement of May 2026 to the Planning Inspectorate; project pages and press releases on nationalgrid.com. Prysmian, SSEN Transmission and NKT publications for the counterparties.

Every figure is a promoted fact in the web, each with its fact id, source and locator behind it, drawn from the 54 documents cited.